Installation of 12-inch export pipeline connecting the ultra-deepwater Profundo development with shallow water infrastructure, offshore Brazil.  

Company: Technip Brasil (Petrobras)

Location: Santos Basin, Atlantic coast of southeastern Brazil 

1180 m

Max. water depth 

Scope of work 

  • Detailed design & engineering 
  • Procurement & supply (coated line pipe, anodes, valves & connectors) 
  • Fabrication (PLRs, span supports, ILBV & PLET) 
  • Crossing preparations 
  • Installation of 50-km, 12-inch export line (started with ILBV at shallow end & terminated with dual hub PLET at deep end) 
  • Span rectification  
  • Flooding, cleaning, gauging & testing 

50-km

12-inch export line

Image
2012 Capixaba Profundo

Specials & challenges 

  • EPCI project in joint venture with Technip Brasil 
  • Extremely tight schedule 
  • Anode taper design complete with interface system for in-house 3LPP coating  
  • Multiple free spans & crossings  
  • New double-joint welding system with sour service design/welding requirements 
  • New see-saw roller boxes & field joint coating cooling system for acceptable pull times 
  • Steep slopes, curves & tight lay tolerances due to existing infrastructure and coral outcrops 
  • ILBV (c/w mudmats) installation with 140-m-long stinger at 28 m water depth 
  • PLET installation in 1180 m water depth in congested area with tight installation tolerances 

140-m-long 

stinger at 28 m water depth 

Image
2012 Capixaba Profundo
Image
2012 Capixaba Profundo
Image
2012 Capixaba Profundo