Single-lift removal of the complete 30,000-tonne Gyda platform from the Norwegian North Sea and transport to shore for recycling. 

Company : Repsol Norge AS 

Location : Southern Norwegian sector of the North Sea 

Single-lift removal of 18,400-tonne topsides & 11,500-tonne jacket

First-time removal of entire platform (topsides & jacket)

First-time removal of conductors

Scope of work 

  • Engineering, preparation, removal & disposal (ERPD) of 18,400-tonne processing/drilling/accommodation topsides & 11,500-tonne jacket (incl. all 32 conductors & subsea template)  
  • Transfer of topsides & jacket to Iron Lady for load-in to Aker Solutions yard at Stord, Norway 
  • Transfer of conductors and template to Sagro yard at Vlissingen, the Netherlands 
  • Pre-lift preparations (incl. removal & separation of under-deck caissons) 
  • Design, fabrication & installation of bearing blocks to accommodate horseshoe lifting tools 
  • Topsides leg cutting 
  • Jacket pile & leg cutting 

18,400-tonne 

processing/drilling/accommodation topsides

 11,500-tonne 

jacket

Image
2021 Gyda Platform Removal

Specials & challenges 

  • First-time removal of complete platform utilising all Pioneering Spirit lift systems (TLS, JLS & 5000-tonne crane)  
  • Offshore scope completed in 12 days across two campaigns (removal, transport & load-in of complete platform) 
  • Design, fabrication & welding of bearing blocks (horseshoe connections), lift trunnions with fixed spreader bars (jacket lift) & various frames (conductor removal) 
  • Welding of bearing brackets with own crew in combination with Covid restrictions 
  • Lift & transport of jacket in near-vertical position (60 degrees JLS angle) 
  • Optimisations for topsides load-in to accommodate future toppling of the structure 
  • Fabrication of jacket lift trunnions (capacity of 5500 tonne each) 
  • Removal & reclining of 32 conductors (76 m each) 

5500 tonne

Fabrication of jacket lift trunnions

Image
2021 Gyda Platform Removal
Image
2021 Gyda Platform Removal
Image
2021 Gyda Platform Removal
Image
Welding of the brackets
Image
Arrival in the Gyda field
Image
Preparations for topsides load-in
Image
Topsides transfer to Iron Lady
Image
Skidding topsides onto the quayside
Image
Gyda jacket removal
Image
Direct jacket transfer to quayside
Display on a map
Off