Time-critical sequence removal of multiple platform facilities – weighing more than 34,000 tonnes – from the North Sea’s Tyra field and delivery to recycling yards in Denmark and the Netherlands.
Company : Total Denmark
Location : Danish North Sea, 225 km west of Esbjerg
Removal : 2020 (Phase 3), 2022 (Phase 4)
Complex cutting & lifting activities in congested live field
Very limited air gap during lift due to subsidence
Complex removal sequence versus tight delivery deadlines
14,000-tonne
TEA processing/accommodation topsides
7600-tonne
TWA processing/accommodation topsides
Specials & challenges