Record-breaking single-lift removal of the 24,000-tonne Brent Delta topsides – first of the four iconic Brent field platform removals – and delivery to the UK for recycling.  

Company : Shell UK 

Location : UK North Sea, 186 km northeast of Lerwick, Shetland 

140 m

Water depth

Scope of work 

  • Engineering, preparation & removal of 24,000-tonne Brent Delta topsides 
  • Transfer of topsides from Pioneering Spirit to Iron Lady for load-in to Able UK disposal yard, Hartlepool, England 
  • Pre-lift preparation work (incl. design of underdeck lift points & strengthening of the module support frame) 
  • Cutting & seafastening of the platform legs 
  • Design & fabrication of lifting yokes, support stools & grillage 

24,000-tonne 

Brent Delta topsides

Image
2017 Brent Delta Topsides Removal

Specials & challenges 

  • Heaviest offshore lift in history (as of 2017) 
  • First commercial offshore lift utilising Pioneering Spirit’s complete Topsides lift system (16 lifting beams) 
  • Complete cutting & seafastening of the legs prior to lift 
  • Efficient design, fabrication & installation of lift points, & strengthening while platform still being decommissioned 
  • Design & fabrication of lift yokes & stabilisation frames 
  • Design, fabrication & installation of leg support structures 
  • Design, fabrication & installation of 3x GBS leg covers & navigation aid 
  • Design of barge grounding bed at disposal yard for topsides transfer to quayside

3x 

GBS leg covers & navigation aid

Image
2017 Brent Delta Topsides Removal
Image
2017 Brent Delta Topsides Removal