Single-lift removal of the complete 23,000-tonne Ninian Northern platform from the North Sea and transport to shore for disposal.
Company : CNRI
Location : North Sea, 160 km northeast of Shetland
Removal : 2020 (topsides), 2022 (jacket)
First-time in-port transfer of topsides from Pioneering Spirit to Iron Lady
First commercial lift with new Jacket lift system
14,200-tonne topsides & 8100-tonne jacket
First-time use of horseshoes & extension pieces for topsides lift
Complete cutting of platform legs one year prior to the single lift