Transport and installation of the Zingst and Darß offshore substations and supporting jackets for the OST-6-1 offshore grid connection in the German Baltic Sea.

Company: HSI consortium (end client 50Hertz) 

Location: German Baltic Sea (15 km off the Darß peninsula)

Water depth: 16 – 18 metres

Critical offshore infrastructure for Baltic's largest wind development

Installation of 2 offshore substations with combined production capacity of +900 MW

All structures installed during 18-day campaign

First-time installation of suction bucket jackets

Offshore substations installed with jacket lift system 

 

Scope of work

  • Project management, engineering and preparation for transport, offshore transfer and installation operations
  • Transport of the Gennaker west (Darß) and east (Zingst) suction jackets and offshore substations (OSS) on separate asset barges
  • Installation of both suction bucket jackets and OSS with the jacket lift system (JLS) 
  • Post-installation survey, structural completion and associated specialist suction-bucket, grouting and marine activities
Image
Gennaker HSE 2026 03

Project specials

  • First installation of topsides using the JLS
  • First commercial Allseas installation of jackets founded on suction buckets
  • Rostock selected as a Baltic buffer port to separate North Sea transport from installation sequence
  • Buffer-port preparation and staged call-off of the four assets to installation sites
  • Offshore transfers from the asset barges to Pioneering Spirit using spacer barges and tugs
  • BIAS dynamic-positioning mode to mitigate scour risk at shallow water installation sites

Project challenges

  • Shallow-water installation with Pioneering Spirit at 13.5 m draught (minimal under-keel clearance prevented use of topsides lift system)
  • Complex offshore transfers in an exposed offshore environment, requiring coordinated positioning of asset barges, unmanned spacer barges, tugs and support vessels
  • Tightly constrained transfer and installation areas influenced by existing and future turbines, the Baltic Cable, a Natura 2000 area and prepared seabed excavations
  • Scour and sedimentation risk from Pioneering Spirit’s thrusters, requiring controlled vessel orientation, low-thrust movements and BIAS DP operation
  • Boulders and silt at Gennaker East with potential to obstruct / limit suction-bucket penetration
  • Autumn Baltic Sea weather conditions 

Photo credits: Tom Schünemann & DanPilot/Chris Hansen

Image
Transfer of Gennaker east OSS
Image
Passage under Storebælt Bridge
Image
Jacket arrival at buffer port (Rostock)
Image
Installation of Gennaker west jacket
Image
Installation of Gennaker west OSS
Image
Installation of Gennaker east jacket
Image
Installation of Gennaker east OSS
Image
Set down of Gennaker east OSS
Image
The two OSS will deliver 900 MW of clean energy to shore