Installation of 120-kilometre gas gathering line for the Trion field development – Mexico’s first ultra-deepwater oil production project – tying into the Sur de Texas pipeline laid by Allseas in 2018

Company: Woodside Energy (formerly BHP)

Location: Gulf of Mexico (350 kilometres northeast of Altamira, Mexico)

Water depth: 80 - 1900 metres

Mexico’s first ultra-deepwater production project

Ties in to the Allseas-laid Sur de Texas system

Scope of work 

  • Installation of 120-kilometre, 16-inch pipeline (incl. PLET & PLEM)
  • Design & fabrication of J-mode PLET & S-mode PLEM
  • Design & fabrication of overtrawlable PLEM protection structure
  • DMA startup with S-Mode PLEM
  • Supply of strakes for spans
  • Procurement of pipeline anodes
  • Transport line pipe to Mexico from CPW in Greece
  • Setup pipe haul hub in Northeast Mexico for pipe logistics
  • Flooding, gauging & testing subcontract
  • Fabrication of buckle arrestors
Image
Solitaire

Specials & challenges 

  • First end PLEM start-up in S-Mode; installation on pre-installed mudmat
  • First project following double-joint factory upgrade
  • Logistics
  • Weather preparation – GoM hurricanes