Engineering, preparation, removal & disposal of the original Valhall DP drilling platform (topsides, jacket and bridges) from the Norwegian North Sea.

Company : Aker BP 

Location : North Sea, 280 km off the Norwegian Coast 

70 m

Water depth 

Scope of work 

  • Engineering, preparation, removal & disposal (EPRD) of 6800-tonne drilling topsides (DP), 4350-tonne jacket & connecting bridges 
  • Pre-lift preparation work (incl. underdeck scaffolding & removal of obstructions under cellar deck for access to lift points, installation of shear brackets and uplift restrainers on legs, cutting & removal of caissons, removal of bridge obstructions, installation of bridge pivot guide, NDT critical joints) 
  • Cutting of grouted platform legs 
  • Transfer of topsides from Pioneering Spirit to cargo barge & load-in to disposal yard (Stord, Norway) 

 6800-tonne 

drilling topsides (DP)

4350-tonne

jacket & connecting bridges 

Image
2022 Valhall DP Platform Removal

Specials & challenges 

  • Offshore preparations carried out in both “cold” and “live” oil and gas platform environments in Valhall field 
  • Removal of decommissioned facilities from live field  
  • First-time deployment of all Pioneering Spirit’s lift systems on the same project (TLS, JLS & 5000-tonne crane) 
  • Topsides 1500-tonne difference between estimated lift weight (5300 tonne) and actual lift weight (6800 tonne) requiring modifications to selected load-in barge 
  • Tight vertical clearances between Pioneering Spirit and topsides during removal due to field subsidence 
  • Small horizontal clearances between TLS and platform (small platform results in lift points close to legs and caissons) 
  • Pre-lift activities and welding close to the splash zone 
  • Barge-to-barge ‘rollover’ transfer method for topsides load-in operation to yard 

1500-tonne 

difference between estimated lift weight