Engineering, preparation, removal & disposal of the original Valhall QP accommodation platform (topsides, jacket and bridge) from the Norwegian North Sea. 

Company : Aker BP 

Location : Southern Norwegian North Sea

Removal : 2019 (topsides & bridge), 2021 (jacket) 

Lightest topsides lift, to date, using TLS

Small vertical clearances during topsides removal due to small air gap 

Jacket removal in 2 sections using in-house spreader bar & clamp system

Scope of work 

  • Engineering, preparation, removal & disposal of 3800-tonne accommodation topsides (QP) & connecting QP-DP bridge (2019)
  • Engineering, preparation, removal & disposal of 3300-tonne QP jacket (2021)
  • Pre-lift preparation work for topsides removal (incl. removal of under deck obstructions for access to lift points, installation of shear brackets & uplift restrainers on legs, cutting & removal of caissons, removal of bridge obstructions, installation of bridge pivot guide)
  • Cutting of grouted platform legs
  • Design & fabrication of TLS yokes interfaces, navigational aid & grillages
  • Design & fabrication of X & Y stoppers’ interfaces (for lift yokes) to suit bottom of cellar deck (without adding steel to the topsides)
  • Delivery of topsides, bridge & jacket to disposal yard for recycling (Stord, Norway) 
Image
2019 Valhall QP Platform Removal

Specials & challenges 

  • First job for Pioneering Spirit under frame agreement with Aker BP to provide transport, installation, and removal services for the Valhall oil field 
  • Lightest offshore lift operation for Pioneering Spirit’s Topsides Lift System  
  • First-time bridge removal (using special purpose crane) 
  • Offshore preparations carried out in both “cold” and “live” oil and gas platform environments in Valhall field 
  • Removal of decommissioned facilities from live field  
  • Two years of engineering, planning and pre-lift preparations 
  • Small vertical clearances during topsides removal due to small air gap (15.4 m to LAT) with Pioneering Spirit at maximum draught of 27 m 
  • Small horizontal clearances between TLS and platform (small platform results in lift points close to legs and caissons) 
  • Jacket removal in 2 sections with the 5000-tonne crane using in-house spreader bar & clamp system 
Image
2019 Valhall QP Platform Removal
Image
2019 Valhall QP Platform Removal
Image
2019 Valhall QP Platform Removal
Image
Removal of upper jacket section
Image
Lift of lower jacket section
Image
Jacket load-in to disposal yard
Image
Welding of shear brackets on legs
Image
Bridge removal
Image
Navigation aid installation
Display on a map