Engineering, preparation, removal & disposal of the original Valhall QP accommodation platform (topsides, jacket and bridge) from the Norwegian North Sea. 

Company : Aker BP 

Location : North Sea, 280 km off the Norwegian Coast 

Removal : 2019 (topsides & bridge), 2021 (jacket) 

70 m

Water depth 

Scope of work 

  • Engineering, preparation, removal & disposal (EPRD) of 3800-tonne accommodation topsides (QP) & connecting QP-DP bridge 
  • Pre-lift preparation work (incl. underdeck scaffolding & removal of obstructions under cellar deck for access to lift points, installation of shear brackets and uplift restrainers on legs, cutting & removal of caissons, removal of bridge obstructions, installation of bridge pivot guide, NDT critical joints) 
  • Cutting of grouted platform legs 
  • Design & fabrication of TLS yokes interfaces, navigational aid & grillages 
  • Design & fabrication of X & Y stoppers’ interfaces (for lift yokes) to suit bottom of cellar deck (without adding steel to the topsides) 
  • Transfer of topsides from Pioneering Spirit to cargo barge & load-in to disposal yard (Stord, Norway) 

3800-tonne 

accommodation topsides (QP)

Image
2019 Valhall QP Platform Removal

Specials & challenges 

  • First job for Pioneering Spirit under frame agreement with Aker BP to provide transport, installation, and removal services for the Valhall oil field 
  • Lightest offshore lift operation for Pioneering Spirit’s Topsides Lift System  
  • First-time bridge removal (using special purpose crane) 
  • Offshore preparations carried out in both “cold” and “live” oil and gas platform environments in Valhall field 
  • Removal of decommissioned facilities from live field  
  • Two years of engineering, planning and pre-lift preparations 
  • Small vertical clearances during topsides removal due to small air gap (15.4 m to LAT) with Pioneering Spirit at maximum draught of 27 m 
  • Small horizontal clearances between TLS and platform (small platform results in lift points close to legs and caissons) 
  • Jacket removal in 2 sections with the 5000-tonne crane using in-house spreader bar & clamp system 

27 m

Pioneering Spirit at maximum draught

Image
2019 Valhall QP Platform Removal
Image
2019 Valhall QP Platform Removal
Image
2019 Valhall QP Platform Removal
Display on a map
Off