Largest installation project in Allseas’ history, Nord Stream 2 is a dual 1200 km-long offshore natural gas pipeline that runs through the Baltic Sea from the St Petersburg region of Russia to the Baltic coast in north-east Germany connecting Europe to the world’s largest reserves in Northern Russia. 

Company : Nord Stream 2 AG 

Location : Baltic Sea (Russia, Finland, Sweeden, Denmark & Germany) 

15 – 210 m 

Water depth

Scope of work 

  • Pre-lay route survey & seabed preparations (incl. installation of approx. 1000 mattresses) 
  • Pipe haul from marshalling yards & associated logistics 
  • Installation of approximately 2300 km of 48-inch concrete-weight-coated pipeline 
  • As-laid survey 

 

2300 km 

48-inch concrete-weight-coated pipeline 

Image
2018 Nord Stream 2

Specials & challenges 

  • Largest pipeline installation scope in Allseas’ history  
  • Mobilise fleet to Baltic Sea 
  • Modification of Audacia to anchor lay vessel for shallow water scope in German waters 
  • Permit restrictions in German waters resulting in 3-month installation window and no DP in water depths less than 20 m (~75 km of the route) 
  • Curved pipelay through Finnish waters over preinstalled span & cable crossings 
  • Pipe haul of approx. 200,000 pipe joints 
  • Severe Baltic Sea winter conditions 

 200,000 