Installation of largest diameter (44-inch) pipeline in Australian waters, part of major new system connecting the Wheatstone development with the nation’s first liquefied natural gas (LNG) hub in Onslow, Western Australia.

Company: Chevron Australia  

Location: Northwest Shelf, Western Australia 

150 m

Max. water depth

Scope of work 

  • Installation 220-km, 44-inch concrete-weight-coated (CWC) export pipeline 
  • Installation 34-km, 24-inch CRA-clad production pipelines 
  • Installation 34-km, 14-inch CRA-lined utility pipelines 
  • Installation 34-km, 6-inch carbon steel MEG flowlines 
  • Design, fabrication & installation of subsea structures (incl. 14x PLET, 6x ILTs, ~40 counteracts) 
  • Flooding, gauging & testing (FGT) of pipeline system 

220-km, 44-inch 

concrete-weight-coated (CWC)

Image
2015 Wheatstone Upstream Development

Specials & challenges 

  • Installation of largest & heaviest offshore diameter pipeline (44-inch) in Australian history 
  • Above surface tie-in of 44-inch CWC trunkline 
  • Complex flowline installation scope with multiple startups & laydowns 
  • Multiple crossings with existing live lines 
  • Shore pull-in through micro-tunnel  
  • Design & fabrication of ILTs & PLETs 
  • CRA welding scope with extensive NDT programme 

44-inch

CWC trunkline is above surface tie-in

Image
2015 Wheatstone Upstream Development