Allseas maiden pipelay project in China, comprising the installation of multiple pipelines and structures for the deepwater Lingshui 17-2 gas field development in the South China Sea. 

Company : Chinese Offshore Oil Engineering Company (CNOOC) 

Location : 150 km south of Hainan Island, South China Sea 

1535 m 

Max water depth

Scope of work 

  • Installation of 90 km, 18-inch export line with PLET at the deep end 
  • Installation of 4x 10-inch flowlines (in total 53 km) & 6 PLETs (J-mode) 
  • Installation of 3x 4.5-inch MEG lines (in total 19 km) & 6 PLETs (S-mode) 

3x 4.5-inch 

MEG lines

Image
2020 Lingshui 17-2

Specials & challenges 

  • Allseas’ first project in China  
  • Installation of 2.3-km, 4.5-inch pipeline in 500 m water depth with PLETs floating at both ends 
  • Short preparation time (less than 6 months) 
  • Testing weather conditions (high humidity, large swells, typhoon season) 
  • High flexibility of 4.5-inch MEG lines 

4.5-inch 

MEG lines

Image
2020 Lingshui 17-2
Image
2020 Lingshui 17-2
Image
2020 Lingshui 17-2
Display on a map
On