Installation of new flowline system for the latest expansion of the Malampaya deepwater gas field in the Philippines

Company: Prime Energy Resources 

Location: Philippines, West of Palawan

Water depth: 700 - 1110 metres

Complex deepwater scope comprising CRA flowlines and umbilicals

First-time deepwater hammer spread

Steep seabed profiles and tight installation tolerances

Extensive in-house fabrication scope 

Scope of work 

  • Installation of 3x 12-inch CRA flowlines (~17 km)
  • Fabrication and installation of 6x CRA PLETs
  • Transportation and installation of and 3x umbilicals (~45 km) and 20x flying leads
Image
Flowline installation by Audacia on MP4

Specials & challenges 

  • Major SURF scope
  • Project marks Allseas return to the Philippines for first time in 25 years
  • Installation of deepwater umbilicals routed over challenging seabed terrain
  • Multiple steep escarpments crossings
  • Installation of deepwater hammered foundation and counteract piles
  • FLETs & umbilical termination assemblies connected to wells via jumpers & flying leads
  • CRA scope with stringent quality requirements
Image
FLET loadout at AFBV Heijningen
Image
Deepwater hammer spread & structure installation by Fortitude
Image
Deployment of fast-frame and pile installation
Image
Flowline installation on MP4
Image
J-mode installation of first FLET
Image
Touchdown of first FLET for MP4
Image
Dolphin CRA trials
Image
Small diameter pipe internal weld inspection tool trials
Image
AUT FLET tests
Image
Camingo-1 flowline installation
Image
Sixth & final FLET
Display on a map
On